March has been a positive month for client feedback and our work at BlueScope Steel's No 5 Blast Furnace Shutdown was no exception.
Both Mark O'Keefe and Warren Hinde achieved exceptions results whilst working on the 501 Bearing Change. To add a level of complexity, this work had never before been attempted whilst the plant was operating.
As such, Allfab was on critical path whilst working on the conveyor. Our dedicated crews put in a great effort to finished well before the allocated time.
Well done to Mark, Waz and their teams who worked diligently to ensure the work was completed ahead of schedule.